AI server foundry Quanta (2382) continues to build its own power for US factories. This time, through its U.S. subsidiary, two sets of fuel cell microgrid systems were purchased, totaling approximately US$367 million. In addition to California, the company also purchased Tennessee. Together with the first two purchases, a total of about $950 million was spent. The power consumption of new generation AI cabinets has increased significantly, and power equipment has become the focus of investment for Quanta’s production expansion.
California $250 million, Tennessee $117 million! Both systems include technical services
Quanta’s U.S. subsidiary Quanta Manufacturing Nashville (QMN) on the 25th announced on the Public Information Observatoryannouncement, purchasing two sets of fuel cell microgrid systems from Bloom Energy and including technical services. The total amount is approximately US$367 million, which is approximately NT$11.689 billion when converted at the announced exchange rate of 31.85. Among them, the California case is about $249.9 million, and the Tennessee case is about $117.1 million.
According to the announcement, the transaction was negotiated by the undertaking unit and submitted to the chairman for approval for operational needs. "Business Times"reportIt is pointed out that the equipment is expected to be used in new factories in California and Tennessee to meet the testing needs of more high-end servers before shipment.
Three times a total of about $950 million? Quanta will start placing orders in 2024
This is not the first time that Quanta has placed an order with Bloom. In October 2024, QMN announced an additional investment of approximately US$79.75 million to purchase three sets of systems. On December 30, 2025, QMN purchased three more sets for US$502 million, all of which will be used in the B16, B18, and B19 factories in California.
Based on the amounts announced in these three announcements, Quanta’s purchase of fuel cell microgrids from Bloom totaled approximately US$950 million, or approximately NT$29.6 billion. In recent years, California's power supply stability has declined due to wildfires and aging power grids; Quanta has purchased fuel cells three times to meet its power needs for AI server production.
Capital expenditure next year is expected to reach 45 billion: expansion focus shifts to test-end power
Quanta held a Dharma lecture on the 11thexpress, the customer's AI product route has been planned for two years. The computing power density of the new generation cabinet is higher, and the testing and power consumption of a single cabinet have increased significantly. Therefore, the power and testing capacity of overseas factories continue to be expanded.
The company estimates capital expenditures in 2027 to be approximately NT$40 billion to NT$45 billion, slightly higher than this year. According to a report by the Industrial and Commercial Times, the focus of expansion will shift to power facilities on the testing side. Capital expenditures in the first three quarters of this year were approximately 34.6 billion yuan, of which factories in California and Thailand accounted for nearly 80%.
this article Quanta (2382) deploys AI server production capacity in two places in the United States and spends US$367 million to build its own microgrid first appeared in Chain News ABMedia。